Search the Public Notice PortalThe early morning piece of a quiet residential road was shattered unexpectedly last week by muddy construction lorries trundling along their street.
The chair of Mylor Bridge Parish Council has accused Cornwall Council of "deceit" after construction traffic caused disruption on Robert Rundle Way during work on the Little Greystones housing development.
The entrance to the site at the top of Robert Rundle Way, Mylor Bridge (Image: Staff)
Cllr John Symons, who also chairs the planning committee, accused the authority of “deceitful and appalling” behaviour, claiming a traffic management plan was revoked just 48 hours after approval.
He said the parish council fought hard for a Construction Environment Management Plan (CEMP) to be included as a planning condition.
He alleged that developers applied to discharge condition three – the traffic management plan – and Cornwall Council agreed without consultation.
In an email to fellow councillors, he said his phone didn't stop ringing once the work started last week.
Robert Rundle Drive, Mylor Bridge (Image: Staff)
He described how Robert Rundle Way was left covered in mud and residents struggled to access their homes.
“Cars were reversing into mud, which was being brought into driveways and homes,” he said.
The revoked plan, according to Cllr Symons, would have directed construction traffic away from Robert Rundle Way, using an alternative gate off Bell's Hill. Instead, lorries have been using the residential street since work began.
The development, which will deliver 37 affordable homes for local people, is expected to take two years to complete.
The turkey oak at the entrance to the site was chopped down despite protests from locals (Image: Diane Bell/Facebook)
It has already sparked controversy after a 180-year-old oak tree at the site entrance was felled last week despite protests from residents who campaigned to save it.
Gilbert & Goode, the company behind the project, strongly denied that any such traffic management order was ever in place.
Sue Warwick, managing director, issued the following statement saying: “Gilbert & Goode is proud to deliver a development that will provide 37 much-needed affordable homes for the local community.
“With over 23,000 households currently on Cornwall’s housing register, this project represents a significant contribution toward addressing the county’s housing needs.
“During the planning process, Cornwall Council determined that access via Robert Rundle Way was the only safe and appropriate route available, and this approach was formally approved. At no stage was an alternative access route mandated as a condition of planning consent.
“We fully acknowledge that construction activity can cause disruption, and we remain committed to minimizing its impact.
"Our team will continue to engage with residents throughout the build, ensuring that concerns are addressed promptly and transparently.
The entrance to Robert Rundle Drive. Cllr Symons says site access was supposed to be further up Bell's Hill. (Image: Staff)
"Gilbert & Goode has a proven track record of delivering high-quality homes while maintaining strong relationships with local communities.”
Cllr Symons says construction should halt until stricter traffic controls are reinstated, while the developer maintains its approach is safe and compliant.
Read more
- First Bust! All services in Cornwall gone by February next year with loss of 275 jobs
- Police hunting moped riders who assaulted man that challenged dangerous riding
- Dog attack on beach in Cornwall leaves woman injured: Appeal
He told the Packet: “The Parish Council fought hard to stop all construction traffic using Robert Rundle Way from the start of this application, so condition 3 was put in place that the field next to Robert Rundle Way would be used as the storage site with a constructed lane out to Bells Hill that would bypass Robert Rundle Way.
“The PC approved the application with this in the CEMP [traffic plan] which was granted on 13th August 48 hours later PA25/06197 was submitted to discharge condition 3 leaving out the site storage and the access lane, so ALL construction traffic has to use Robert Rundle Way.
“The PC are consultees, but the residents and the PC were not consulted and didn’t know about the discharge until work started.
“This is why I feel it has been deceitfully done.”
The Packet had asked Cornwall Council for a response.
Share